Subscribe to our mailing list

e-mail Format

Peter Lupunga

The work was well done and many villagers came to witness the installation. During the past people in the village were suffering from water borne diseases but they are sure that now this will be the past history.

There are no good roads in the area and movement is very difficult. There are no trees in the village and they ask for tree seeds. People in the area are poor but they are good farmers.


on behalf of

João

Date of Installation

2021-07-02

Area

Euthini

District

Mzimba

GPS

-11.433923, 33.416461     see on map

Pump no.

21176

Dist. from Factory (km)

138.0

Village Head / Group Village Head

Khwetha

Contact (phone no.)

0992330161

Previous Water Source

Open well

Installation Type

New

Well Depth (m)

9.28

Water Depth (m)

1.92

Pump Length (m)

9.08

Dist. from Furthest Household (m)

391

No. of People Served

120

Pump Dedication / Donor

HireVibes